[Oct-2023] CSM-001 Certification with Actual Questions from TorrentValid [Q61-Q79]

Share

[Oct-2023] CSM-001 Certification with Actual Questions from TorrentValid

Updated CSM-001 Dumps PDF - CSM-001 Real Valid Brain Dumps With 119 Questions!

NEW QUESTION # 61
Select which option best completes the following statement. __________ is all about response to change.

  • A. Change management
  • B. Agile
  • C. Customer satisfaction
  • D. Planning

Answer: B


NEW QUESTION # 62
What does the Sprint Backlog consist of?

  • A. Selected Backlog Items and Tasks
  • B. User Stories, only.
  • C. Test cases
  • D. Use Cases

Answer: A


NEW QUESTION # 63
From the activities given, which is the latest step in sequence of the Scrum framework?

  • A. Daily scrum
  • B. Sprint planning
  • C. Sprint retrospective
  • D. Sprint review

Answer: C


NEW QUESTION # 64
Agile software development also promotes industry best practices that _______________ and

  • A. Emphasize managers; stakeholder involvement
  • B. Emphasize software developers; manager involvement
  • C. Emphasize team members; partner involvement
  • D. Emphasize teamwork; customer involvement

Answer: D


NEW QUESTION # 65
________________ constitute the Sprint Backlog and are often estimated in hours?

  • A. Features
  • B. Tasks
  • C. User Stories
  • D. Use Cases

Answer: B

Explanation:
Explanation


NEW QUESTION # 66
The correct sequence of events in using Scrum framework is as follows:

  • A. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
  • B. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
  • C. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
  • D. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective

Answer: A


NEW QUESTION # 67
___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.

  • A. Stakeholder
  • B. Scrum Owner
  • C. Scrum Master
  • D. Product Owner

Answer: C


NEW QUESTION # 68
Select which of the following statements is the most accurate.

  • A. The Scrum Master is responsible for summarizing the Sprint Retrospective discussion and reporting the discussions to Senior Management.
  • B. The Scrum Master is responsible for facilitating and participating in the Sprint Retrospective
  • C. The Product Owner is responsible for summarizing the Sprint Retrospective discussion and reporting the discussions to Senior Management.
  • D. The Scrum Master is responsible for documenting the Sprint Retrospective discussion.

Answer: B


NEW QUESTION # 69
True or False: Scrum teams may include cross-functional teams?

  • A. False
  • B. True

Answer: B


NEW QUESTION # 70
It's come to your attention that some team members feel that Carlos is a negative influence on the team.
You can certainly understand why - he believes that everything is doomed. What should you do?

  • A. Remove Carlos from the team.
  • B. Ignore him and hope it goes away
  • C. Escalate the issue with the higher authorities
  • D. Use Carlos as an asset, particularly during risk identification

Answer: D


NEW QUESTION # 71
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?

  • A. This forces Product Owners to focus on what is really important for the team to develop.
  • B. A Sprint cycle is not enough time for senior management review and approve changes
  • C. The development team must be able to limit the Product Owner authority
  • D. The development team cannot meet their Sprint commitment to complete work if requirements are changing

Answer: A


NEW QUESTION # 72
On a new Scrum Team, the Development Team tell the Scrum Master that they don't feel the need for retrospectives. Which answer is correct?

  • A. Discuss with product owner
  • B. None of above
  • C. Start doing retrospectives

Answer: B


NEW QUESTION # 73
Which three activities will a Product Owner likely engage in during a Sprint?

  • A. Run the daily Scrum
  • B. Provide feedback
  • C. Answer questions from the Development Team about items in the current Sprint
  • D. Work with the stakeholders
  • E. Prioritize the Development Team's activities.
  • F. Update the Sprint burndown chart

Answer: B,C,D


NEW QUESTION # 74
Which role in Scrum is responsible to prioritize Product Backlog?

  • A. Lead Auditor
  • B. Product Owner
  • C. ScrumMaster
  • D. Development team

Answer: B

Explanation:
Explanation/Reference:
Reference: https://www.visual-paradigm.com/scrum/what-is-product-backlog-in-scrum/


NEW QUESTION # 75
Select which option best completes the following statement: _____________ is all about response to change.

  • A. Change management
  • B. Agile
  • C. Customer satisfaction
  • D. Planning

Answer: B


NEW QUESTION # 76
When many Scrum Teams are working on a project, what best describes the definition of "done"?

  • A. Each Team defines and uses its own
  • B. Each Team uses its own but must make it clear to all other Teams
  • C. It depends
  • D. All teams must use the same definition

Answer: D


NEW QUESTION # 77
How could the team and other stakeholders know if a product backlog item is done?

  • A. Ask the Manager
  • B. They should ask to the member's development team
  • C. They should compare what was done, against the definition of Done established by the Scrum Team
  • D. Ask the Product Owner

Answer: C

Explanation:
Explanation/Reference:


NEW QUESTION # 78
Which objectives are covered as part of Sprint Planning?

  • A. Reviewing current functionality that binds the software solution
  • B. Recalculating empirical velocity, adjusting team capacity accordingly, and projecting end dates
  • C. Updating the scope of the release with all Sprints, end dates, and costs
  • D. Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to doit.

Answer: D


NEW QUESTION # 79
......

Pass Your CSM-001 Exam Easily With 100% Exam Passing Guarantee: https://freedumps.torrentvalid.com/CSM-001-valid-braindumps-torrent.html